Township of Severn is undertaking culvert rehabilitation on Foxmead Road approximately 220 metres east of Uhthoff Line (between Uhthoff Line and Burnside Line). 

This culvert rehabilitation will require a full closure beginning Monday, October 21, 2024 and is anticipated to take 4-6 weeks for completion. 

This work will include: 

  • rehabilitation of the existing culvert
  • installation of new retaining walls
  • reconstruction of the roadway including a new guiderail system

Road access and service impacts 

A full closure at the project site is required for this work. There will be no through access on Foxmead Road between Uhthoff Line and Burnside Line. Detour signage will be in place utilizing Uhthoff Line and Thorburn Road as an alternate route.

Foxmead Road Closure

Emergency Services (Fire, Paramedics, and Police), County of Simcoe, and the Simcoe County Student Transportation Consortium (SCSTC) have been advised of this closure. If your child is impacted as a result of this closure the SCSTS will reach out to you directly. You can also contact them by visiting simcoecountyschoolbus.ca.  

Waste management services and curbside collection will continue to be provided by the County of Simcoe for the length of the project in coordination with the project contractor. 

Severn appreciates your patience, understanding, and cooperation during this important construction project.

Project details and updates will be posted on our News and Notice page. Subscribe to updates to stay informed.

Project contacts

Project engineer
Andrew Dawson, P.Eng
Project Engineer
R.J. Burnside & Associates Ltd.
Phone: 1-800-265-9662
Email: andrew.dawson@rjburnside.com

Staff contact
Colt Newman, C.E.T.
Manager of Capital Projects
Township of Severn
Phone: 705-325-2315 x254
Email: cnewman@severn.ca

Contractor
Tom Thomason
Construction Manager
K.J. Excavating Inc.
Phone: 705-327-7991
Email: tthomason@kjexcavating.ca